Adequacy of Front 80-T for the berthing of 140,000 DWT crude oil tankers at the Repsol terminal, Tarragona.

The project includes conceptual, basic and detailed engineering for the installation of two crude oil loading arms at Repsol Tarragona's 80-T front to operate as a back-up system for the existing ones at the 80-S front.

A laser scanning was carried out in the field for subsequent generation of a point cloud from which the 3D design of the new facility was made, including the interconnection of the arms with the crude I and crude II collectors. Updating of P&IDs, associated instrumentation, electrical connection of the arms, piping design and support through 3D model, RFQ and tabulation of new loading arms, economic estimation and project execution planning.